Pallet racking regulations
The rules for racking sit in one set of regulations, one HSE guide and one European standard. Here is what each asks of the person running the warehouse.
Get a quoteThe law: PUWER 1998
Racking counts as work equipment, so the 1998 Provision and Use of Work Equipment Regulations, known as PUWER, apply. Two regulations do most of the work. Regulation 5 says equipment must be maintained in an efficient state and in good repair. Regulation 6 says equipment exposed to conditions that cause deterioration must be inspected at suitable intervals and after exceptional events, such as a heavy truck strike, and that the result is recorded and kept until the next inspection.
Regulation 2 defines inspection as a visual or more rigorous check by a competent person (PUWER reg 2). The law does not set the interval. That comes from the guidance.
The guidance: HSE's HSG76
HSE's free guide HSG76, Warehousing and storage has a storage systems chapter that most inspectors work from. In short, it expects:
| Duty | What it means day to day | Where it comes from |
|---|---|---|
| Appoint a person responsible for racking safety | One named person who knows the installation, sets the inspection interval and makes sure damage is acted on. | HSG76 |
| Keep load notices up | Each run shows the safe load per beam level and per bay, and the configuration it applies to. | HSG76 |
| Report damage at once | Drivers and pickers tell the responsible person about any knock, however small, the same shift. | HSG76 |
| Run weekly visual checks | A trained member of staff walks the racking and records what they find. Busy sites may check more often. | HSG76 |
| Book an expert inspection | At least every 12 months, by a technically competent person, with a written report. | HSG76, PUWER reg 6 |
| Keep the records | Inspection reports, the damage register and repair records, at least until the next inspection. | PUWER reg 6, HSG76 |
Inspections are normally made from the floor, unless the inspector sees signs of trouble higher up. For automated high-bay stores, the guide allows at least a fifth of the installation to be inspected each year, so that all of it is covered within five years (HSG76 PDF).
The damage ratings
HSG76 sorts damage into three bands, so everyone on site reads a report the same way (HSG76 Table 11):
Green
Within limits. Record it and keep an eye on it at the next check.
Amber
Offload, isolate and repair as soon as possible. Not done in four weeks, it becomes red.
Red
Offload and isolate at once. The bay stays out of use until it is repaired.
The European standard
BS EN 15635 covers the application and maintenance of steel static storage systems. It is the source of the damage limits inspectors measure against, the idea of a person responsible for storage equipment safety, and the expectation that the user keeps installation and load information. You don't need a copy to run a compliant site, but your inspector should be working to it.
Who counts as competent
HSE accepts an in-house person, the supplier or an independent inspector, as long as they are technically competent. In practice most sites book an inspector who holds the SEMA Approved Rack Inspector (SARI) qualification from the Storage Equipment Manufacturers' Association, and you can check an individual's card on the association's verification tool. This site is an independent matching service and is not part of, approved by or linked to that association.
Load notices and changes to layout
Every run of racking should carry a notice showing the safe load per beam level and per bay for the configuration actually installed. Move a beam level, add a bay or change frame heights and the notice may no longer be true. Changes need the manufacturer's data or the supplier's approval before they are made (HSG76). Inspectors check notices on every visit.
Records to keep
- The last expert inspection report and the one before it
- Weekly check sheets (our printable checklist covers these)
- The damage register, with dates reported and dates repaired
- Repair records and any supplier approvals for layout changes
For what an inspection costs, see the cost guide; for what follows the report, see racking repairs.
What site managers ask about the rules
Is a racking inspection a legal requirement?
The duty to inspect is in law: PUWER regulation 6 requires inspection of work equipment that is exposed to conditions causing deterioration. HSG76 is guidance, but HSE inspectors use it to judge whether you have done enough.
How often should pallet racking be inspected?
Weekly visual checks by your own staff and an expert inspection at least every 12 months. The person responsible for racking safety can set a shorter interval where damage is frequent.
Does the inspector have to be independent?
No. HSE accepts a competent person from your own staff, your racking supplier or an independent firm. What matters is that they are technically competent and write the findings up.
What happens if we skip the annual inspection?
It is a breach of PUWER and of the general duties in the Health and Safety at Work etc. Act 1974. HSE can serve improvement or prohibition notices, which are published on its public register, and prosecute after a collapse.
Find an inspector near your site
Four boxes and you are done. We pick an inspection firm that covers your postcode and tell you its name; nothing about you is passed on until you say yes. There is no charge to you.
Pallet Racking Inspection is an independent matching service and does no inspecting itself. Fees, dates and terms are agreed between you and the firm.
Received
- Watch your inbox for the name of an inspection firm near the site.
- Reply yes to be put in touch, or no to stop.
- If yes, the firm gets in touch to talk through bays and access.